NAICS
236220 - Commercial and Institutional Building Construction
PSC
Z2AA - REPAIR OR ALTERATION OF OFFICE BUILDINGS
Category
Facility Related Services (4.4)
Posted
2024-05-03
Deadline
2024-06-03
Place of performance
JB Andrews, Maryland 20670, UNITED STATES

Description

The project includes but is not limited to replacement of deteriorating (27) hydronic floor mounted fan coil units to include associated fittings, piping, valves, and accessories. (2) 7.5 ton rooftop package units to include associated, disconnect switches, circuit breakers, conduits, wirings, piping, valves, temperature sensors, controls, and accessories. (2) Mini-split type a/c unit to include associated disconnect switches, circuit breakers, conduits, wirings, piping and accessories located in IDF room and locker room. (4) Ceiling exhaust fans and associated accessories located in first floor toilet male and female rooms, locker room, and weather office room– 104. (1) Baseboard heater unit and associated accessories located in second floor corridor 100 entryway.

The new work includes of the following:

1) Provide and install (27) new ceiling cassette type fan coil units to include associated fittings,

valves, piping, insulation, hanger support, digital control, and accessories. Provide fan coil units

that match the existing chiller unit brand.

2) Modify existing fan coil units piping (cold/hot) as required for proper installation of new ceiling cassette type units. Remove any unused piping, fittings, valves, and associated accessories. Where required, drywall is removed add layer of ½ rigid expanded polystyrene (EPS) foam.

3) Provide and install (2) new 7.5 ton rooftop package units to include associated, disconnect

switches, circuit breakers, conduits, wirings, piping, valves, temperature sensors, digital controls,

and accessories. Provide necessary equipment required for ductwork cleaning. At no time both

units will be down. Provide and install (2) pole metal mounted for disconnect switches.

4) Provide and install new (2) mini-split type a/c unit with cooling only to include associated

disconnect switches, circuit breakers, conduits, wirings, piping and accessories located in IDF

room and locker room. Existing housekeeping pads may reused if good condition is acceptable.

5) Provide and install new (4) ceiling exhaust fans located in first floor toilet male and female rooms, locker room, and weather office room– 104.

6) Provide and install new baseboard heater unit and associated accessories located in second floor corridor 100 entryway.

7) Provide and install new ceiling exhaust fan in second floor room 205; shower and toilet rooms to include circuit breakers, conduits, wirings, and associated accessories.

8) Provide and install new dedicated outdoor air system (DOAS) unit to include associated

ductwork, housekeeping pad, disconnect switch, circuit breakers, conduits, wirings, control,

sensors, and accessories. Provide design for DOAS unit to include ductwork and electrical

systems. Perform load calculation to determine appropriate size unit.

9) Provide and install new acoustical ceiling tiles and associated accessories that match the existing patterns and finishes.

10) Modify existing electrical panel to adapt serve new DOAS unit and ceiling exhaust fans.

Existing electrical wiring may reused if capacity is adequate and in good condition.

Building will remain occupied during construction. Very important, heating, cooling, and dehumidification shall be maintained in the Air Traffic control operation room during this project.