ClickCease Acquisition Management Complex Phase V (AMC-V) | Closed - MatchAwards

Acquisition Management Complex Phase V (AMC-V)

Status
Closed, the response deadline passed on Aug 12, 2024
Agency
United States Department of the Army
Office
LOUISVILLE, USA
Notice type
Combined Synopsis/Solicitation
Solicitation number
W912QR24-AMCV-WPAFB
NAICS
541330 - Engineering Services
PSC
C219 - ARCHITECT AND ENGINEERING- GENERAL: OTHER
Category
Construction Related Services (4.2)
Posted
2024-07-31
Deadline
2024-08-12
Place of performance
Wright Patterson AFB, Ohio, UNITED STATES

Description

Description:

A market survey is being conducted to make acquisition decisions about this future project and to determine if there are a reasonable number of interested small business concerns to set this future project aside for them. If your firm is a Small Business, certified HUBZone, 8(a), Woman-Owned Small Business, or Service-Disabled Veteran Owned Small Business and you are interested in this project, please respond appropriately.

Proposed Requirement:  This announcement is open to all business regardless of size. The Louisville District, U.S. Army Corps of Engineers has a need to award a firm fixed standalone contract to an Architectural & Engineering firm to develop a 35% design. Contract to also include options for: 65% design, 90% design, Corrected Final design, and Certified Final design and Construction Phase Support Services (CPSS). The estimated construction cost for the project is between $100,000,000 and $250,000,000.

The selection authority will, in order of preference, list the firms most highly qualified to perform the work. At least one of the most highly qualified firms will be requested to submit a proposal. Negotiations will begin with the most highly qualified firm in the final selection. If a mutually satisfactory contract cannot be negotiated, the contracting officer will terminate negotiations with that firm and initiate negotiations with the next most preferred firm on the list. If a mutually satisfactory contract is negotiated with the most preferred firm, no additional negotiations will occur. Only one firm will be selected.

Firms will be selected for negotiation based on demonstrated competence and qualifications for the required work. If necessary, secondary selection criteria will be used as a tiebreaker between firms considered as technically equal. Significant emphasis will be placed on the A/E’s quality control procedures, as the district will perform the quality assurance role only. Estimated start date is January 2025.

In accordance with FAR 36.604 and supplements thereto, and upon final acceptance or termination, all A/E services contracts above $35,000 will receive a performance evaluation. An interim performance evaluations may be prepared at any time. Performance evaluations will be maintained for use in future source selections for A/E services.

Project Specific Information:  The Design Acquisition Management Complex Phase V (AMC-V) project will: demolish 3 facilities an approximately total of 29,533 SM (317,893 SF) to clear the site location; construct a primary facility of 19,900 SM (214,201.82 SF) which includes administrative space, special purpose space, miscellaneous infrastructure connections, and all necessary support; sitework includes the repair of the storm drainage and the resurface of the existing parking lot.

The preliminary building concept design consists of reinforced concrete foundation and floor slab, structural frame, roof system and secure space. Facilities will be designed as permanent construction in accordance with the DoD Unified Facilities Criteria (UFC) 1-200-01, General Building requirements. This project will comply with DoD Antiterrorism/Force Protection requirements per UFC 4-010-01 and Intelligence Community Directive 705 (ICD 705).