description: Repair Building S-1832, Camp Casey, Korea (MATOC Only). United States Department of the Army. Solicitation W90VN824R0062. NAICS 236220 - Commercial and Institutional Building Construction. Deadline 2024-08-14. Repair Building S-1832, Camp Casey, Korea (MATOC Only) 2.1.1. Structural Work 2.1.1.1....
canonical: https://matchawards.com/dept_of_the_army/posts/112845705816880951
og:image: https://matchawards.com/home_logo.png
og:image:width: 130
og:image:height: 130
twitter:card: MatchAwards.com
twitter:image: https://matchawards.com/home_logo.png
og:site_name: MatchAwards
og:type: article
og:title: Repair Building S-1832, Camp Casey, Korea (MATOC Only) | Closed
og:url: https://matchawards.com/dept_of_the_army/posts/112845705816880951
og:description: Repair Building S-1832, Camp Casey, Korea (MATOC Only). United States Department of the Army. Solicitation W90VN824R0062. NAICS 236220 - Commercial and Institutional Building Construction. Deadline 2024-08-14. Repair Building S-1832, Camp Casey, Korea (MATOC Only) 2.1.1. Structural Work 2.1.1.1....
og:image: https://matchawards.com/system/accounts/avatars/000/000/092/original/04da5de8c6ff714b.png?1638996022
og:image:width: 120
og:image:height: 120
twitter:card: summary
---

# Repair Building S-1832, Camp Casey, Korea (MATOC Only)

Status

Closed, the response deadline passed on Aug 14, 2024

Agency

[United States Department of the Army](/dept%5Fof%5Fthe%5Farmy)

Office

APO, USA

Notice type

Combined Synopsis/Solicitation

Solicitation number

W90VN824R0062

NAICS

[236220 - Commercial and Institutional Building Construction](/groups/212)

PSC

5680 - MISCELLANEOUS CONSTRUCTION MATERIALS

Category

[Facility Related Materials (4.3)](/categories/facilities-and-construction/facility-related-materials)

Posted

2024-07-24

Deadline

2024-08-14

Place of performance

Camp Casey, Korea, Gyeonggi, KOREA, SOUTH

## Description

Repair Building S-1832, Camp Casey, Korea (MATOC Only)

**2.1.1\. Structural Work**

2.1.1.1\. Repair by replacing existing column w/ steel column.

**2.1.2\. Architectural Work**

2.1.2.1\. Floor Work

2.1.2.1.1\. Replace deteriorated existing floor tile with new PVCT including VCB or

wooden base as shown on new floor plan & interior finish schedule.

2.1.2.1.2\. Replace deteriorated existing CMT with new FCT including cement bond coat,

waterproof membrane, mortar bed as shown on floor plans, section and details drawings.

2.1.2.2\. Interior & Exterior Wall Work

2.1.2.2.1\. Replace deteriorated existing gypsum wall board walls with new GWB wall (GWB,

normal, water resistant or 'X' type) including metal studs, metal clips and metal bar as shown

on floor plans, sections and detail drawings.

TP I-1

2.1.2.2.2\. Paint all interior walls and designated exterior surfaces as shown on floor plan,

detail drawings and interior finish schedule.

2.1.2.2.3\. Replace deteriorated existing GCWT with new including cement bond coats,

waterproof membrane, plastering w/metal lath and waterproof GWB as shown on floor plans

and sections.

2.1.2.3\. Interior & Exterior Ceiling/Roof Work

2.1.2.3.1\. Replace deteriorated existing ceiling with new acoustical tile ceiling and gypsum

wall board (GWB, normal, water resistant or 'X' type) ceiling including ceiling suspension

system as shown on floor plan, sections and finish schedule.

2.1.2.3.2\. Paint on all interior ceiling surfaces as shown on interior finish schedule and

section.

2.1.2.3.3\. Replace deteriorated existing insulations with new at bottom of the roof surfaces

including fluted metal linings as shown on floor plan, sections and interior finish schedule.

2.1.2.3.4\. Replace existing metal roof with new protected metal roof at storage facility area

including 2-ply of 12THK plywood sheathings, roof insulations and fluted metal linings at

bottom of the roof as shown on elevation, sections and finish schedule.

2.1.2.3.5\. Repair by installation of fluid applied waterproofing system on existing metal roof

at the straight metal roof area and new protected metal roof at storage facility area including

replacement of wooden fascia boards, metal rain gutters and downspouts as shown on floor

plan, elevations and finish schedule.

2.1.2.4\. Misc. Work

2.1.2.4.1\. Replace deteriorated existing doors and door frames with new including hardware

sets as shown on new floor plan and door schedule.

2.1.2.4.2\. Replace deteriorated existing windows with new including horizontal fireproof type

mini blinds.

2.1.2.4.3\. Replace deteriorated existing columns with new as shown on floor plan.

\*See structure drawings.

2.1.2.4.4\. Replace deteriorated existing fire extinguishers cabinets (FEC) with new as shown

on floor plans and detail drawing.

2.1.2.4.5\. Replace deteriorated existing all toilet accessories with new as shown on floor

plans, schedule and detail drawings.

2.1.2.4.6\. Replace interior & exterior signages with new as shown on floor plan, elevations

and signage schedule.

2.1.2.4.7\. Replace deteriorated existing bulletin board with new as shown on floor plan,

detail drawing and signage schedule.

2.1.2.4.8\. Clean the existing main entrance aluminum double doors.

2.1.2.4.9\. Replace deteriorated existing concrete stoop and metal canopy with new including

wooden step inside the door as shown on new floor plan and pictures.

**2.1.3\. Mechanical Work**

2.1.3.1\. Repair the heating and cooling system by installing new split heat pump system,

split air conditioning unit, electric wall heater, electric unit heater, valves, piping, insulations,

controls, equipment support (Conc. pad), and all associated accessories for HVAC system

as shown on drawings.

TP I-2

2.1.3.2\. Repair the ventilation system by installing new split compact dedicated outdoor air

system, exhaust fans, controls, diffusers, register, ducts, insulations, outside air intake

louver with birdscreen, motorized damper and all associated accessories for ventilation

system as shown on drawings.

2.1.3.3\. Repair the plumbing system by installing new electric domestic hot water heater,

domestic hot water recirc. pump, electric water cooler, domestic cold and hot water piping

system, insulation, sewer and vent piping system, water hammer arrests, floor drain, floor

cleanout including plumbing fixtures, and all associated accessories as shown on drawings.

**2.1.4\. Electrical Work**

2.1.4.1\. Replace deteriorated existing interior/ exterior lighting fixtures, exit lights, toggle

switches, wires and conduits with new.

2.1.4.2\. Replace existing watthour meter, current transformers, panelboards, receptacles

w/cover plates, associated wiring & conduits with new.

2.1.4.3\. Replace deteriorated existing safety switches, motor controllers, junction boxes,

control/power wires and conduits for mechanical systems with new.

2.1.4.4\. Replace deteriorated fire alarm control system with new addressable fire alarm

control and mass notification system panel, manual pull station, smoke detector & relay

module, antenna, visual/signal strobes (15 or 75 candela), microphone, speaker (wattage as

req'd) device, fire alarm building transmitter, antenna, surge protector, and associated wiring

and conduit.

2.1.4.5\. Replace deteriorated existing telecommunication system including telephone

terminal board, telephone/data outlets w/cover plates, terminal blocks, equipment rack

and associated wire & conduit with new.

2.1.4.6\. Replace existing exterior underground telecommunication line, accessories with

new.

2.1.4.7\. Replace existing exterior power distribution system with new including pad mounted

transformer.

**Army Contract Writing System (ACWS) Transition Information for Offerors**

1. The Army Contracting Enterprise (ACE) is in the process of deploying new solicitation and contract writing software to Army contracting offices worldwide. Known as the Army Contract Writing System (ACWS), this modern software suite will soon replace most existing Army contract writing systems, including the system used to create and release this Solicitation.
1. During this transition period, Offerors are hereby advised:
1. The Contracting Office may use any combination of contract writing systems to create and release documents related to this solicitation (e.g. solicitation amendments and awards, if any). Due to this:
1. 1. This solicitation may contain different offer submission instructions than other solicitations released by the same Contracting Office (e.g. requiring offer submission via the PIEE Solicitation Module vs. e-mail). Offerors should review all offer submission instructions contained in the solicitation documents and direct any questions or concerns to the Contract Specialist or Contracting Officer.
1. 1. If the Contracting Office switches contract writing systems prior to award, documents you receive from the Contracting Officer or view on SAM.gov or other forums may appear noticeably different than the initial solicitation or previous solicitations or awards from the same Contracting Office. This is normal and expected.
1. 1. A change between contract writing systems may cause important information concerning solicitation response (amendments) or accepted terms (awards) to take on different formatting or appear in different parts of later documents issued. Offerors shall review all documents carefully to locate this important information and direct any questions or concerns to the Contract Specialist or Contracting Officer.
1. The Government does not intend to use the transition between contract writing systems to effect any changes to solicitation or award terms and conditions without accompanying document narratives explicitly stating such changes are deliberate and desired. While the Contract Specialist and Contracting Officer will take care to minimize or eliminate any inadvertent changes when adapting to the new contract writing software, you, as the Offeror, may still be the first to spot such errors. Therefore, Offerors shall:
1. 1. Notify the Contracting Officer immediately if any observed changes, removals, or additions affect your award eligibility, violate or alter existing quote/proposal terms, or could affect Contract performance post-award.
1. 1. Take special care to ensure all fill-in Clauses are populated and remain populated across documents received from the Contracting Office throughout the Solicitation and Award process.
1. 1. Contact the Contracting Officer listed on the first page of the solicitation or solicitation amendment for guidance if you notice or suspect any inadvertent change has occurred between document issuances.
1. The Contracting Officer will correct problems affecting award documents (if any) via bilateral modification, at no cost to the Contractor. Any such modification will reconcile the award with the latest version of this solicitation reflecting deliberate action by the Contracting Officer (e.g. the first issuance if no amendments, or the latest amendment with accompanying narratives), inclusive of any documented pre-award negotiations or accepted supplemental offer terms.
1. In the unlikely event a network disruption, contract writing system error, or financial system error threatens timely award of the requirement set forth in this solicitation, the Contracting Officer:
1. 1. May elect to use alternative mechanisms to obligate funds and allow work or deliveries to legally begin to the benefit of, and with legal protection for, both parties.
1. 1. Will incorporate the latest version of this Solicitation into such mechanisms to serve as a framework for contract execution until any such system problems are resolved.
1. 1. Will ensure any action taken does not conflict with the stated offer evaluation and award methodology of this requirement.
1. 1. Will issue a complete, properly-formatted award accurately reflecting this requirement and all applicable terms and conditions once systems return to normal.

## Attachments

* [Attachment 1](https://sam.gov/api/prod/opps/v3/opportunities/resources/files/09bf960e75e94450802dd1b4e3b6b233/download)
* [Attachment 2](https://sam.gov/api/prod/opps/v3/opportunities/resources/files/2540844393e54cc0a25beb67aed63832/download)
* [Attachment 3](https://sam.gov/api/prod/opps/v3/opportunities/resources/files/77b5bb352cd24762b3ed286cb7b56008/download)
* [Attachment 4](https://sam.gov/api/prod/opps/v3/opportunities/resources/files/a1658daec6cb4c109e9d89c99d1399b2/download)
* [Attachment 5](https://sam.gov/api/prod/opps/v3/opportunities/resources/files/f2cad1078b684f75a57120e17dc6ea6b/download)

[Source notice](https://sam.gov/opp/8de899a7f2fc46a08e0799bfb484515c/view)

[More from United States Department of the Army posted in July 2024](/dept%5Fof%5Fthe%5Farmy/archive/2024-07)

## More lists

* [Government Contracts Available Now: Open Federal and State Opportunities](/contracts)
* [Construction Government Contracts Available Now](/contracts/construction)

```json
{"@context":"https://schema.org","@type":"Demand","name":"Repair Building S-1832, Camp Casey, Korea (MATOC Only)","description":"Repair Building S-1832, Camp Casey, Korea (MATOC Only) 2.1.1. Structural Work 2.1.1.1. Repair by replacing existing column w/ steel column. 2.1.2. Architectural Work 2.1.2.1. Floor Work 2.1.2.1.1. Replace deteriorated existing floor tile with new PVCT including VCB or wooden base as shown on new floor plan \u0026 interior finish schedule. 2.1.2.1.2. Replace deteriorated existing CMT with new FCT including cement bond coat, waterproof membrane, mortar bed as shown on floor plans, section and details drawings. 2.1.2.2. Interior \u0026 Exterior Wall Work 2.1.2.2.1. Replace deteriorated existing gypsum wall board walls with new GWB wall (GWB, normal, water resistant or 'X' type) including metal studs, metal clips and metal bar as shown on floor plans, sections and detail drawings. TP I-1 2.1.2.2.2. Paint all interior walls and designated exterior surfaces as shown on floor plan, detail drawings and interior finish schedule. 2.1.2.2.3. Replace deteriorated existing GCWT with new including cement bond coats, waterproof membrane, plastering w/metal lath and waterproof GWB as shown on floor plans and sections. 2.1.2.3. Interior \u0026 Exterior Ceiling/Roof Work 2.1.2.3.1. Replace deteriorated existing ceiling with new acoustical tile ceiling and gypsum wall board (GWB, normal, water resistant or 'X' type) ceiling including ceiling suspension system as shown on floor plan, sections and finish schedule. 2.1.2.3.2. Paint on all interior ceiling surfaces as shown on interior finish schedule and section. 2.1.2.3.3. Replace deteriorated existing insulations with new at bottom of the roof surfaces including fluted metal linings as shown on floor plan, sections and interior finish schedule. 2.1.2.3.4. Replace existing metal roof with new protected metal roof at storage facility area including 2-ply of 12THK plywood sheathings, roof insulations and fluted metal linings at bottom of the roof as shown on elevation, sections and finish schedule. 2.1.2.3.5. Repair by installation of fluid applied waterproofing system on existing metal roof at the straight metal roof area and new protected metal roof at storage facility area including replacement of wooden fascia boards, metal rain gutters and downspouts as shown on floor plan, elevations and finish schedule. 2.1.2.4. Misc. Work 2.1.2.4.1. Replace deteriorated existing doors and door frames with new including hardware sets as shown on new floor plan and door schedule. 2.1.2.4.2. Replace deteriorated existing windows with new including horizontal fireproof type mini blinds. 2.1.2.4.3. Replace deteriorated existing columns with new as shown on floor plan. *See structure drawings. 2.1.2.4.4. Replace deteriorated existing fire extinguishers cabinets (FEC) with new as shown on floor plans and detail drawing. 2.1.2.4.5. Replace deteriorated existing all toilet accessories with new as shown on floor plans, schedule and detail drawings. 2.1.2.4.6. Replace interior \u0026 exterior signages with new as shown on floor plan, elevations and signage schedule. 2.1.2.4.7. Replace deteriorated existing bulletin board with new as shown on floor plan, detail drawing and signage schedule. 2.1.2.4.8. Clean the existing main entrance aluminum double doors. 2.1.2.4.9. Replace deteriorated existing concrete stoop and metal canopy with new including wooden step inside the door as shown on new floor plan and pictures. 2.1.3. Mechanical Work 2.1.3.1. Repair the heating and cooling system by installing new split heat pump system, split air conditioning unit, electric wall heater, electric unit heater, valves, piping, insulations, controls, equipment support (Conc. pad), and all associated accessories for HVAC system as shown on drawings. TP I-2 2.1.3.2. Repair the ventilation system by installing new split compact dedicated outdoor air system, exhaust fans, controls, diffusers, register, ducts, insulations, outside air intake louver with birdscreen, motorized damper and all associated accessories for ventilation system as shown on drawings. 2.1.3.3. Repair the plumbing system by installing new electric domestic hot water heater, domestic hot water recirc. pump, electric water cooler, domestic cold and hot water piping system, insulation, sewer and vent piping system, water hammer arrests, floor drain, floor cleanout including plumbing fixtures, and all associated accessories as shown on drawings. 2.1.4. Electrical Work 2.1.4.1. Replace deteriorated existing interior/ exterior lighting fixtures, exit lights, toggle switches, wires and conduits with new. 2.1.4.2. Replace existing watthour meter, current transformers, panelboards, receptacles w/cover plates, associated wiring \u0026 conduits with new. 2.1.4.3. Replace deteriorated existing safety switches, motor controllers, junction boxes, control/power wires and conduits for mechanical systems with new. 2.1.4.4. Replace deteriorated fire alarm control system with new addressable fire alarm control and mass notification system panel, manual pull station, smoke detector \u0026 relay...","url":"https://matchawards.com/dept_of_the_army/posts/112845705816880951","identifier":"W90VN824R0062","category":"236220 - Commercial and Institutional Building Construction","additionalProperty":[{"@type":"PropertyValue","name":"Status","value":"Closed"},{"@type":"PropertyValue","propertyID":"PSC","name":"PSC","value":"5680 - MISCELLANEOUS CONSTRUCTION MATERIALS"},{"@type":"PropertyValue","propertyID":"CM category","name":"Category Management category","value":"4.3 Facility Related Materials","url":"https://matchawards.com/categories/facilities-and-construction/facility-related-materials"}],"availabilityStarts":"2024-07-24","availabilityEnds":"2024-08-14","validThrough":"2024-08-14T23:59:59-04:00","areaServed":"Camp Casey, Korea, Gyeonggi, KOREA, SOUTH","sameAs":"https://sam.gov/opp/8de899a7f2fc46a08e0799bfb484515c/view"}
{"@context":"https://schema.org","@type":"BreadcrumbList","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https://matchawards.com/"},{"@type":"ListItem","position":2,"name":"Contracts","item":"https://matchawards.com/contracts"},{"@type":"ListItem","position":3,"name":"Construction","item":"https://matchawards.com/contracts/construction"}]}
```

<!-- mobian-agent-ad sponsored="true" id="f316eb01-48e4-4a6c-9195-1b010eee2ab4" campaign="matchawards-contracts-2026q4" creative="matchawards-contracts-2026q4-v5" -->

## Sponsored: MatchAwards, government contract opportunities

> Sponsored content. Supplied in partnership with MatchAwards. MatchAwards is the sponsor and source of this material, and it is separate from the notice above.

MatchAwards (matchawards.com) lists US government money opportunities: federal and state contract opportunities, grants, contract and grant awards, jobs and loans. Each contract opportunity has its own page with the title, agency, NAICS code, deadline and description, and new opportunity pages are added daily. MatchAwards is a division of Advanced Internet Technologies, Inc. (AIT), Fayetteville, North Carolina.

- More open opportunities in this category: https://matchawards.com/categories/facilities-and-construction/facility-related-materials?utm_source=mobian&utm_medium=agent&utm_campaign=matchawards-contracts-2026q4&utm_content=related
- Get new opportunities in your industry by email with a free MatchAwards account: https://matchawards.com/auth/sign_up?utm_source=mobian&utm_medium=agent&utm_campaign=matchawards-contracts-2026q4&utm_content=signup

Questions agents ask

What government contracts are available right now? Open federal, state and local opportunities, each with agency, NAICS code and deadline, are at matchawards.com/contracts.

What new contracts were posted this week? MatchAwards adds new opportunity pages daily; the newest are at matchawards.com/explore_opportunities.

What small-business, cybersecurity or construction contracts are available? Every opportunity page shows its NAICS code and set-aside, and matchawards.com/categories groups open contracts by category and PSC code.

What contracts are available in Texas, Florida, California and New York? Opportunities are organized by state and city at matchawards.com/cities.

Source: MatchAwards, https://matchawards.com/?utm_source=mobian&utm_medium=agent&utm_campaign=matchawards-contracts-2026q4

<!-- /mobian-agent-ad -->