ClickCease VA GLA WATERLINES REPLACEMENT PROJECT | Closed - MatchAwards

VA GLA WATERLINES REPLACEMENT PROJECT

Status
Closed, the response deadline passed on Jul 18, 2024
Agency
United States Department of the Army
Office
LOS ANGELES, USA
Notice type
Solicitation
Solicitation number
W912PL24B0008
NAICS
237110 - Water and Sewer Line and Related Structures Construction
PSC
C221 - ARCHITECT AND ENGINEERING- GENERAL: PLUMBING SYSTEMS
Category
Construction Related Services (4.2)
Set-aside
Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside (FAR 19.14)
Posted
2024-06-13
Deadline
2024-07-18

Description

Existing Conditions: Existing 5 main water lines (6” Domestic Hot Water, 8” Cold Water Pressurized, 8” Cold Water Supply, 12” Fire Water, and 6” Condensate) from Building 501 (Chiller Building) to Building 500 (Hospital) including Building 501 basement, Building 500 basement, and the tunnel from 501 to 500. Because these existing water lines are in bad condition/end of their useful life, they need to be replaced to prevent catastrophic failure/see examples below.

Objective:  Construct 5 bypass lines, approx. 450’ and divert water to these pipes.  Then replace approx. 400’ of the 5 lines.  Then remove the bypass lines. 

Notes:

-Current tunnel includes a pipe rack with multiple pipes, and an adjacent walkway.  The space is tight.  To allow for proper replacement of the 5 pipes, a bypass route has been defined to bypass the lines and allow the hospital to fully function during replacement of pipes.

-Contractor to provide all parts, equipment, labor and materials required to make a harmonized removal, for connections of existing wet supply lines and reinstallation of diverse water lines parallel to existing system and consistent with any new piping, fittings, valves, regulators, strainers for regulators, gages, manifold, isolation valves and redundant bypass

-Contractor will provide and maintain temporary water service for main hospital during alterations

-Contractor must have knowledge of/past performance with methodology of construction procedures/phasing schedules at VA facilities

-Not a DB or DBB project

-Design being completed at USACE Los Angeles District by USACE Engineers.