Process Vacuum Pump
- Status
- Closed, the response deadline passed on Jan 26, 2026
- Agency
- United States Department of the Air Force
- Office
- TINKER AFB, USA
- Notice type
- Presolicitation
- Solicitation number
- C26-021
- NAICS
- 333912 - Air and Gas Compressor Manufacturing
- PSC
- 4310 - COMPRESSORS AND VACUUM PUMPS
- Category
- Machinery & Components (5.1)
- Posted
- 2026-01-23
- Deadline
- 2026-01-26
- Place of performance
- S Coffeyville, Oklahoma 73145, UNITED STATES
Description
76 CMXG is requesting the purchase of the following item(s).
1. The addition of an oil-lubricated rotary screw vacuum pump to the existing system, along with an integrated control panel to enable fully redundant operation between the two pumps.
2. The contractor shall provide a complete turnkey solution, including all materials, labor, site preparation, delivery, installation, and commissioning of a fully operable process vacuum system.
3. The requested equipment item descriptions/specifications are outlined below
1. Vacuum Pump Specifications:
a. Equipment:
o Provide a new Quincy QSV-530 rotary screw vacuum pump or equivalent oil-seal screw pump that meets the following requirements as a minimum.
o Nominal capacity: 510 CFM.
o Vacuum range: 18" HgV to 29.9" HgV.
o Electrical requirements: 480V, 3-phase, 60 Hz.
o Maximum dimensions: 51" length × 38" width × 44" height (to fit in designated space)
o Drive system: Electric motor with Variable Speed technology, allowing automatic adjustment of motor speed based on process demand
o Operating modes (minimum): Medium PI control loop, Slow PI control, Forced Maximum Speed, and Fixed Speed Control, or equivalent
o Air/oil separation: Oil-separator tank with oil filter; airflow must be cleaned through the air/oil separator filter before discharge
o Cooling system: Oil cooler
o Condensate system: Designed to prevent condensate accumulation in the oil separator, extending oil life
o Inlet valve: Located between the pump and tank; must automatically close during startup when the pump is not yet warmed up, or incorporate an equivalent design to prevent reverse operation
o Cooling and enclosure: Air-cooled, enclosed in sound-insulated bodywork
o Monitoring: Real-time trending of pump metrics over a customizable time period, including (at minimum) inlet pressure, motor speed, power consumption, and oil temperature, displayed in graphical format
o Restart capability: Automatic restart when voltage is restored after a power failure
o Noise level: Maximum 76 dB
b. Warranty:
o Include a comprehensive 2-year warranty covering all parts and labor from the successful start-up date.
o If contractor-performed periodic PM is required to maintain the warranty, all
o associated service costs must be included in the turnkey package.
2.. Integrated Control System Requirements
c. Control Features:
o System must regulate vacuum supply based on real-time demand for optimal energy
efficiency.
o Implement lead/lag sequencing: primary pump operates under standard
demand; secondary pump engages during scheduled downtime or when additional
capacity is needed.
d. PLC Controller:
o Must support OPC UA (preferred) or BACnet protocol for transmitting
performance metrics, diagnostics, and alarms to Tinker AFB’s network.
o Security protocols must comply with ISO 62443
o Controller must support DHCP for IP address assignment or allow IP
reconfiguration via remote access or on-machine HMI
o Enable secure wired remote access via Tinker’s intranet; requires RJ45 port into
control system
e. Automation Capabilities:
• Include full building automation functionalities such as:
o Scheduling
o Alarm notifications
o Historical data logging
o Energy management
o Custom control routines
o Tagging, templating, and hierarchical navigation
f. User Interface:
• Equip with an HTML-based touchscreen interface display:
o Vacuum levels
o Pump temperature
o Operational status, power status, fault codes, last shutdown data
o Elapsed and run hours
o Audio/visual alarms for exceeding operating thresholds
• All operational health data available on the HMI should be included as data tags
g. Panel Construction:
• All components and wiring must be clearly labeled for ease of maintenance.
• Access to system settings must be secured with user profiles, login credentials, and password
protection.
• Incorporate a protected Emergency Stop push button to prevent accidental
engagement.
3. Project Execution Requirements
h. Installation & Commissioning:
o Contractor to furnish all labor, equipment (pump, auxiliary components, piping,etc.), materials, and tools.
o Conduct start-up procedures and full capacity testing to verify operational
readiness.
i. Documentation Deliverables:
• Provide information for PLC Controller:
o Control System Type
o Model, Make, Manufacturer
o Protocol, and Communication port
o MAC Address
o OS/iOS/FW Version (if applicable)
o Host Name
• Provide data tag documentation
o The name or identifier for each data tag
o A description of what each data tag represents. (A brief explanation of what the data measures)
o The data type of each tag. (e.g., Integer, Float, Boolean, String)
o The units of measurement, if applicable. (e.g., RPM, degrees Celsius, mm
o The communication protocol (e.g., OPC UA, Modbus TCP, MTConnect,
o proprietary API)
Admin: Username/password
Customer: Username/password (if required)
o The update frequency or polling rate of each tag (if known)
o Read-only or read-write status
o Any supporting documentation or links describing tag usage.
• Provide comprehensive as-built documentation using industry standards:
o Equipment drawings
o Factory specifications
o Catalog cut sheets for all ancillary items
o Wiring schematics, logic diagrams, interconnect detailsComplete BOM (Bill of Materials)
o O&M manuals, troubleshooting resources, PM schedules
• Submit both printed and digital formats. All drawings must be provided in .dxf or.dwg format.
Training:
o Deliver on-site training for operators and maintenance staff.
o Training must cover system operation and diagnostic interpretation for
preventive maintenance.