<!-- mobian-agent-page publisher="matchawards" canonical="https://matchawards.com/department_of_veterans_affairs/posts/114436594341001995" -->

---
title: H244 Boiler Plant Services - STC | Award to Barque Consulting, LLC - MatchAwards
description: H244 Boiler Plant Services - STC. United States Department of Veterans Affairs. Solicitation 36C26325P0640. NAICS 811310 - Commercial and Industrial Machinery and Equipment (except Automotive and Electronic) Repair and Maintenance. SDVOSB set-aside. STATEMENT OF WORK 1. TITLE: Boiler Plant...
canonical: https://matchawards.com/department_of_veterans_affairs/posts/114436594341001995
og:image: https://matchawards.com/home_logo.png
og:image:width: 130
og:image:height: 130
twitter:card: MatchAwards.com
twitter:image: https://matchawards.com/home_logo.png
og:site_name: MatchAwards
og:type: article
og:title: H244 Boiler Plant Services - STC | Award to Barque Consulting, LLC
og:url: https://matchawards.com/department_of_veterans_affairs/posts/114436594341001995
og:description: H244 Boiler Plant Services - STC. United States Department of Veterans Affairs. Solicitation 36C26325P0640. NAICS 811310 - Commercial and Industrial Machinery and Equipment (except Automotive and Electronic) Repair and Maintenance. SDVOSB set-aside. STATEMENT OF WORK 1. TITLE: Boiler Plant...
og:image: https://matchawards.com/system/accounts/avatars/000/000/015/original/f59915e906ee2b19.png?1638825904
og:image:width: 120
og:image:height: 120
twitter:card: summary
---

# H244 Boiler Plant Services - STC

Agency

[United States Department of Veterans Affairs](/department%5Fof%5Fveterans%5Faffairs)

Solicitation number

36C26325P0640

NAICS

[811310 - Commercial and Industrial Machinery and Equipment (except Automotive and Electronic) Repair and Maintenance](/groups/1092)

PSC

H244 - EQUIPMENT AND MATERIALS TESTING- FURNACE, STEAM PLANT, AND DRYING EQUIPMENT; NUCLEAR REACTORS

Set-aside

[Service-Disabled Veteran-Owned Small Business (SDVOSB) Set-Aside (FAR 19.14)](/contracts/veteran-owned)

Budget

142,209.74

Awardee

Barque Consulting, LLC

Award date

2025-05-01

Place of performance

Fort Pierce, FL 34949, UNITED STATES

## Description

**STATEMENT OF WORK**

**1\. TITLE:** Boiler Plant Instrumentation Calibration, Combustion and Tune, Device Testing and Motor Vibration Analysis services to support the St. Cloud VA Health Care System.

<!-- mobian-agent-ad sponsored="true" id="698adef5-1f3b-4d1a-a071-eba41f8d06ef" campaign="matchawards-contracts-2026q4" creative="matchawards-contracts-2026q4-v5" -->

## Sponsored: MatchAwards, government contract opportunities

> Sponsored content. Supplied in partnership with MatchAwards. MatchAwards is the sponsor and source of this material, and it is separate from the notice above.

MatchAwards (matchawards.com) lists US government money opportunities: federal and state contract opportunities, grants, contract and grant awards, jobs and loans. Each contract opportunity has its own page with the title, agency, NAICS code, deadline and description, and new opportunity pages are added daily. MatchAwards is a division of Advanced Internet Technologies, Inc. (AIT), Fayetteville, North Carolina.

- More open opportunities in this category: https://matchawards.com/categories?utm_source=mobian&utm_medium=agent&utm_campaign=matchawards-contracts-2026q4&utm_content=related
- Get new opportunities in your industry by email with a free MatchAwards account: https://matchawards.com/auth/sign_up?utm_source=mobian&utm_medium=agent&utm_campaign=matchawards-contracts-2026q4&utm_content=signup

Questions agents ask

What government contracts are available right now? Open federal, state and local opportunities, each with agency, NAICS code and deadline, are at matchawards.com/contracts.

What new contracts were posted this week? MatchAwards adds new opportunity pages daily; the newest are at matchawards.com/explore_opportunities.

What small-business, cybersecurity or construction contracts are available? Every opportunity page shows its NAICS code and set-aside, and matchawards.com/categories groups open contracts by category and PSC code.

What contracts are available in Texas, Florida, California and New York? Opportunities are organized by state and city at matchawards.com/cities.

Source: MatchAwards, https://matchawards.com/?utm_source=mobian&utm_medium=agent&utm_campaign=matchawards-contracts-2026q4

<!-- /mobian-agent-ad -->


**2\. OVERVIEW:** The contractor shall provide boiler safety device testing, tuning, inspection, calibration of boiler plant equipment, burners, controls, instruments at the frequency described on the schedule below.

**3\. DEFINITIONS:** 

a.CO – Contracting Officer

b. VA – Department of Veterans Affairs

c. VAHCS – St. Cloud VA Health Care System

d. VATR – Veterans Affairs Technical Representative

e. Contractor Employee – means all Contractor staff, technicians, personnel, subcontractors, or persons working on behalf of the Contractor.

**4\. PLACE OF PERFORMANCE:** 

St. Cloud VA Health Care System, 4801 Veterans Drive, St. St Cloud, MN 56303

1. **PERIOD OF PERFORMANCE:**

This contract will be a Single Award, Firm Fixed Price Service Contract for 1 (One) Base Year from with 4 (Four) Option Years.

1. **QUALIFICATIONS AND SPECIAL CERTIFICATIONS:**
* Certified Technicians shall have completed at least a one-year trade school and have five years successful experience in this field. The experience shall be largely with institutional and industrial boiler plants similar in design to the VAHCS plant.  
  * The VAHCS facility manager/engineer may define and accept equivalent qualifications.
* Technicians shall demonstrate familiarity with and ready access to the current versions of the following references:  
  * NFPA 85, Boiler and Combustion Systems Hazards Code.
  * VHA Boiler Plant Safety Device Testing Manual, most current edition.
* Technicians shall be equipped with portable electronic flue gas analyzers and other test instruments necessary for the required tests and calibrations, to calibrate all instruments, gauges, and transmitters as required herein. All must be calibrated within one month prior to test P-1 and P-4, or recalibration must be completed.  
  * At facilities with programmable digital controls, the technicians must be capable of programming the controls and have the appropriate hardware and software for this.
* Any anticipated sub-contracting work shall be presented in a sub-contracting plan, which is to include the identity of the sub-contractor who will be performing the work. The CO and the VATR must approve, in writing, any sub-contract work prior to its commencement.
* The contractor shall provide experience, past performance, and references with their bid submission.
1. **REGULATIONS / DIRECTIVES / POLICIES:**
* VHA Directive 1810, Boiler and Boiler Plant Operations (most current version)
* VHA Boiler Plant Safety Device Testing Manual (most current version)
* Master Construction Specification, Division 23- Heating, Ventilating and Air Conditioning.
* NFPA 85 - National Fire Protection Association. Boiler and Combustion Systems Hazards Code (most current edition)
* Boiler Safety Device Testing Data Sheet
* Combustion Performance Data Sheet
* Compliance with all state, federal, and local laws
1. **SCOPE OF WORK:**

The Contractor shall provide all transportation, lodging, meals, labor, personnel, equipment, tools, materials, and any resources necessary to provide the following services. Semiannual Boiler Combustion and Tune, Semiannual instrument calibration to include all associated instruments, Semiannual motor vibration analysis, and Annual safety device testing.

**SPECIAL NOTES:** 

 **Only one boiler is allowed to be offline for testing/tune purposes at a time!** 

If a boiler plant emergency, site emergency, or national emergency develops, Contractor will cease testing at the request of site personnel.

**BOILER PERFORMANCE TESTING:**

P1 through P4 shall be completed in accordance with VHA Directive 1810 (Most Current Edition) and VHA Boiler and Associated Plant Safety Device Testing Manual (Most Current Edition)

**P-1 - Semiannual Boiler Combustion and Tune**

**P-2 - Semiannual Instrumentation Calibration**

**P-3 - Semiannual Motor Vibration Analysis**

**P-4 - Annual Safety Device Testing** 

1. Tests will follow VHA Boiler Plant Safety Device Testing Manual procedures verbatim.
1. Technicians shall provide all tools, equipment, and labor necessary to perform inspection, testing, calibrating, and adjustments of burners and boiler and boiler plant controls as specified below.

This shall be done every six or twelve months in accordance with a schedule provided by VAHCS.

1. Instrumentation, monitoring, and data management systems as listed per Directive 1810 Appendix B Table 2 Number 10 shall be calibrated every six months.
1. Provide at least two weeks’ notice to the Boiler Plant Supervisor prior to performing the work.

Work must be conducted when the Boiler Plant Supervisor or his/her designate is available on site to monitor the work.

During normal business hours unless approved by the Boiler Plant Supervisor.

1. VAHCS will have the boilers that are to be serviced prepared for the technicians upon their scheduled arrival.

This includes having the boilers clean of soot and loose scale; fully warmed and at normal steam pressure; steam exhaust silencer system operable. 

1. Performance Testing of Boiler, Burner, Economizer (if provided), Combustion Control, Boiler Plant Instrumentation to be done in accordance with VA Master Construction Specifications, Office of Construction and Facilities Management TIL (Technical Information Library) Division 23.
1. Perform overall visual inspection of systems. Observing any minor or major deficiencies before administering test procedures.

Verify that systems comply with referenced code and VAHCS requirements.

1. Perform tests on each boiler on all main burner fuels.
1. Operate burner(s) on each fuel from low fire to high fire and back to low fire in at least twelve increments and record combustion performance, flue gas oxygen, carbon monoxide, NOx, fuel train pressures, atomizing train pressures, burner pressures, combustion air temperature, flue temperatures and boiler steam output.
1. If required by local emissions authorities, provides services of testing firm to determine NOx and carbon monoxide. Test firm shall be acceptable to emissions authorities.

**NOTE**: If NOx emissions limits are applicable, list the method of testing that is required by local authorities if it differs from the method listed.

1. NOx emissions shall be tested with electronic analyzer reading in parts per million. Analyzer shall be calibrated with certified test gas within three months prior to use. Analyzer shall be accurate to plus or minus 5% of reading.

**Test No. P-1: Combustion and Tune**

1. Operate boiler on each fuel, with economizer (if provided) in service and record data for **at least twelve** evenly spaced steam loads from low fire start to 100% of full steam output, and in the same sequence back to low fire.

Demonstrate performance and efficiency required by paragraphs under Articles, BOILER, BURNER AND FUEL TRAINS, and ECONOMIZER.

1. Demonstrate proper operation of combustion controls, draft control (if provided), feed water level controls, and instrumentation systems (Section 23 09 11, INSTRUMENTATION and CONTROL FOR BOILER PLANT).
1. When flue gas oxygen trim is provided, conduct tests with trim control on manual at the zero trim (null) position (Section 23 09 11, INSTRUMENTATION and CONTROL FOR BOILER PLANT).

After completion of tests with trim control on manual control, repeat the tests on one fuel with the trim control on automatic control.

**Test No. P-2: Calibration** 

1. Check current draw of forced draft fan motor at startup and at 100 percent of maximum boiler load.
2. Current draw shall not exceed full load current stamped on motor nameplate.
1. This test may be combined with Test No. P-1.
2. List of instrumentation and controls to be inspected and calibrated:

(Yokogawa, Rose Mount, Cleaver Brooks, McDaniel, Trerice, Setra, Ashcroft, Ari industries INC, Siemens.)

1. Steam flow transmitters (all).
1. Steam flow recorders/computer readout.
1. Flue gas oxygen sampling, analyzing and recorder/computer readout.
1. Boiler and economizer stack temperature transmitters and recorder/computer readout.
1. Master steam pressure and combustion controllers.
1. Boiler outlet draft controllers.
1. Boiler water level controllers.
1. Feedwater deaerator and condensate storage tank water level controllers including overflow.
1. All pressure and temperature sensors, gauges, and transmitters.

**Test Methods:** 

1. Utilize permanent instrumentation systems for data. All systems shall be operable and in calibration.
2. Utilize portable thermocouple pyrometer furnished and retained by Contractor to measure stack temperature as a verification of permanent stack temperature recorder.
1. Use portable electronic flue gas analyzer to determine constituents of flue gas.

Analyzer shall be capable of measuring oxygen in percent with accuracy of plus or minus 0.5 percent oxygen and carbon monoxide in parts per million (ppm) with accuracy of plus or minus 5 percent of reading (Range 0-l000 ppm).

Obtain oxygen and carbon monoxide readings at each test point.

Calibrate instrument with certified test gases within three months prior to use and immediately after analyzer cell replacement.

1. In Test No. P-1 retain boiler at each load point for a time period sufficient to permit stabilization of flue gas temperature and other parameters.
1. Steam loads for tests may be furnished by the hospital systems, by operation of the steam silencer vent system, or by a combination of the above.
1. Utilize dry bulb and wet bulb thermometers furnished and retained by Contractor for checking combustion air.
1. Smoke testing shall be by visual observation.

If smoke density monitor is not provided, utilize Bacharach Model 21-7006 Smoke Test Kit.

If there is disagreement with the results of these tests, provide qualified observation person and tests in compliance with EPA Reference Method 9 (CFR 40, Part 60, Appendix A).

1. An additional efficiency test will be required, conforming to ASME Performance Test Code PTC 4, if the boiler efficiency determined in the Test P-1 above, does not comply with requirements.

Utilize ASME Test Forms PTC 4.1.a, 4.1.b, and the abbreviated input-output and heat balance methods.

1. Compare the combustion performance data with VAHCS requirements and previous readings. (Flue gas oxygen, carbon monoxide and NOx).

If necessary, make adjustments to the fuel, combustion air controllers, and FGR controller and damper to obtain the required performance.

Record the new performance data. Flash S.D. card with new tune.

**P-3: Motor Vibration Analysis**

1. Check vibration of all electric motors in the boiler plant: burner fans, feed water motors, and condensate motors. Total of 9 motors.
1. **EQUIPMENT LIST:**

**Description**

**Type**

**Make**

**Model/Serial Number**

**Year**

**Boiler 1**

**Fire Tube**

**Cleaver Brooks**

**200-600-200**

**2008**

**Boiler 2**

**Fire Tube**

**Cleaver Brooks**

**200-600-200**

**2008**

**Boiler 3**

**Fire Tube**

**Cleaver Brooks**

**200-600-200**

**2008**

**Boiler 4**

**Fire Tube**

**Cleaver Brooks**

**200-400-200**

**2008**

**DA Tank**

**Industrial Steam**

**Stamp # 13194**

**2008**

**Surge Tank**

**Industrial Steam**

**Stamp # 13138**

**2008**

1. **VA TECHNICAL REPRESENTATIVES:**

 Primary: Boiler Plant Supervisor, 320-252-1670 Ext. 6829

 Alternate: Lead Plant Operator, 320-252-1670 Ext. 6347

**11\. SCHEDULE:**

Contractor shall perform on-site services during normal business hours, 8:00 am to 4:30 pm, Monday through Friday, excluding Federal Holidays, unless otherwise coordinated with the VATR. 

If a holiday falls on Sunday, the following Monday will be observed as the legal holiday. If a holiday falls on Saturday, the preceding Friday is observed as a legal holiday.

The eleven national holidays observed by the Federal Government are:

• New Years Day January 1

• Martin Luther King Jr. Day Third Monday in January

• Presidents Day Third Monday in February

• Memorial Day Last Monday in May

• Juneteenth June 19

• Independence Day July 4

• Labor Day First Monday in September

• Columbus Day Second Monday in October

• Veterans Day November 11

• Thanksgiving Day Fourth Thursday in November

• Christmas Day December 25

• Any additional Federal Holiday declared by the President of the United States

The Contractor shall coordinate with the VATR for an agreed upon work schedule to determine when services can be performed.

Work may be required to be performed outside of normal duty hours if mutually agreed upon by the VATR or designate and Contractor. Any work resulting in hours outside of 8:00 am to 4:30 pm CT because of operational impacts shall occur at no additional expense to the Government.

The Contractor shall provide a minimum of **48-hour notice** of any schedule changes.

**Schedule:** 

Description

Type

Make

Model Number Serial Number

Year

Type of Service

Testing Month(s)

Boiler # 1-3 Boiler # 4,

DA Tank,

Surge Tank

Fire Tube

Cleaver Brooks

200-600-200

200-400-200

2008

Instrument Calibration

April - May October - November

Boiler # 1-3 Boiler # 4,

DA Tank,

Surge Tank

Fire Tube

Cleaver Brooks

Industrial

Steam

200-600-200

200-400-200

2008

Safety Device Testing

October –

November

Boiler # 1-3 Boiler # 4

Fire Tube

Cleaver Brooks

200-600-200

200-400-200

2008

Combustion Tuning

April - May October - November

Boiler # 1-3 Boiler # 4,

DA Tank,

Surge Tank

Fire Tube

Cleaver Brooks

Industrial

Steam

200-600-200

200-400-200

2008

Motor Vibration Analysis

April - May October - November

**12\. REPORTING REQUIRE**